Progress of building Our School

APRIL 2016
SPECIAL NEEDS SCOOL SAMUI NEAR COMPLETION

“Special Needs School – Samui” is almost completed, with only a few further details such as Guttering and railings etc to finish. The result is a magnificent tribute to everyone who has so kindly committed time, effort and funds to this project. READ MORE HERE

THE NEW SPECIAL NEEDS SCHOOL BUILDING
IN BANGRAK – Jan 2016

As can be seen from the photograph, all internal and external rendering has now been completed along with the majority of the internal electrical wiring. The next stage will be for the ceilings to be finished and then the windows and doors to be fitted. If there is anyone out there who could assist with the Landscaping at a later stage it will be much appreciated.

Once again on behalf of The Samui Special Needs Foundation a huge “Thank you” to everyone  for your past help, good luck and good health for 2016 and a wish for your continued support.

Building Progress


Thailand Hotels Assoc. Donation. Read more here…


 October 2015 – Quick update on school construction progress.

This photo taken in October shows the school construction moving ahead nicely.
Windows and doors soon to be added. Stay tuned for more news over time.

october-school-progress

 

19 September 2015 – At last we begin the “Filling in” of the main structure.

Filling in the main structure of the new school

 

 

 

 

 

 

17 May 2015 update: The roof begins to appear! (Thank you Rotary Club of Samui)

School Building_15_05_17_02 School Building_15_05_17_01 School Building_15_05_17_03

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


27 April 2015 update: The school is progressing very nicely showing off a 2nd floor.

20150427151739 School Construction Underway

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


26 March 2015 update:  They are currently working on concrete 1st floor level.

1427338198192 1427338192971 1427338188142

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


15 February 2015 School Update.

Footings for the new school in progress. Very exciting stuff.

10608786_514446182031172_3596674301022076325_o 10257136_514446268697830_2104380665717284825_o

 

 

 

 

 

 

 

 

10945393_506505646158559_6851839037526371159_o

 

 

 

 

 

 

 


Sunday the 25th January saw the long awaited start to the construction of the new Special Needs School here on the island. A colourful ceremony at which the Mayor,Khun Ramnate along with land donor Khun Ngoen Wichaidist and other dignitaries addressed the many guests and supporters began at 2pm and concluded with the pouring of the first concrete foundation stone. These events being blessed by Pra Mongkol Theepacharn, Abbot of Wat Jarn.

10924235_506505649491892_7475487091555145869_o

special needs sod turning

1794793_457750537700737_66461168421221828_n

Khun Dalin Ruangaisoon, founder of the Special Needs School gratefully receiving formal acknowledgement from Khun Ngoen Wichaidist (Former Mayor – Pu Yai Baan of Ban Rak) along with his daughter Khun Ashley of one rai of land (c1,600 sq yds) donated by him. This will be the site of the new purpose built school to be constructed hopefully later this autumn.